别错过23年开云体育官方网站入口查询(2023趋势新闻)

别错过23年开云体育官方网站入口查询(2023趋势新闻)

TasWater’s developer charges approach will change on 1 July 2023. Below we detail the current approach which will continue until that date and the new approach which will introduce an infrastructure contribution charge (previously referred to as a headworks charge). 
For TasWater’s 别错过23年开云体育官方网站入口查询(2023趋势新闻) Policy and related information, please refer to the Price and Service Plan page here.
The following schematic illustrates the three components of developer charges and is an important reference for understanding the two approaches. 

Developer advice

 

别错过23年开云体育官方网站入口查询(2023趋势新闻)

For the period 1 July 2022 to 30 June 2023 (being the first year of PSP4) there will be no change to TasWater’s approach to developer charges (headworks). This is a continuation of the approach in place on 30 June 2022 and provides 12 months to prepare for changes coming into effect on 1 July 2023.

A new policy approach will come into effect from 1 July 2023.

The 别错过23年开云体育官方网站入口查询(2023趋势新闻) Policy approved as part of PSP4 details the old and new policy approaches.

We are currently preparing FAQs and an updated Fact Sheet. These will be released soon.

别错过23年开云体育官方网站入口查询(2023趋势新闻) Policy to 30 June 2023

Under the current policy, spare capacity is made available to Developers at no charge i.e. the third component of developer charges (headworks) does not apply. (This will cease on 30 June 2023.)
Fundamentally, TasWater’s developer charges approach is that a developer only pays Works External costs directly attributable to servicing their specific development (i.e. installs only those assets required to support the development).
TasWater’s policy approach (until 30 June 2023) is summarised as follows:

Sufficient Capacity Insufficient Capacity
Works Internal Developer pays all costs Developer pays all costs
Works external - Extension Developer pays costs of extension required for development Developer pays costs of extension required for development
Works External - Expansion Not applicable Developer pays costs of expansion required for the development

A range of fees and charges also apply, including 别错过开云体育官方入口登录v.6.3.1(2023趋势信息) and ongoing fixed charges relating to new connections.

Isolated Developments
Costs for providing services to developments not involving any extension and/or expansion of existing TasWater systems are paid by the developer. TasWater, at its complete discretion, contribute to the development. 

Advice Regarding Works Required
A developer will only pay Works External costs, assessed by TasWater on a case-by-case basis, directly attributable to servicing their specific development. TasWater will, upon request, provide details of the works required to service a proposed development (including mains connection costs) relating to any Extension or Expansion, enabling independent costing by the developer.

Strategic Opportunities
If TasWater has works programmed that would supply capacity for a development it will discuss this with the developer.

Alternatively, where TasWater makes a strategic decision to install additional capacity, it will fund any additional cost over and above the cost of assets required to service the proposed development.

Existing Planning Permits Containing a Headworks Condition
Developers may apply (through Council) for a minor amendment to their permit (S.56 Land Use Planning and Approvals Act 1993) to allow a development to be reassessed under the current developer charges approach.
In most cases a headworks condition can simply be removed. However, in some instances additional Works External may be required for Expansion (as the removed headworks payment had previously covered this), and a new permit may be required.
The decision to apply to amend a permit or for a new permit is entirely at the developer’s discretion. Developers are encouraged to discuss their options with TasWater prior to submitting any amendment applications to Council.

别错过23年开云体育官方网站入口查询(2023趋势新闻) Policy from 1 July 2023

Updated information sheet is under development.

Was this page useful?

Rate this page

  • Rate as Yes100.00% Yes votes
  • Rate as No0% No votes